Hanceys Turf was contracted to Rebuild 2 Baseball fields through MBRC at Talobilla Park, Redcliffe.
The works covered below show what was involved in the project:
Site Setup
Initial Site setup works we engaged the following prior to any machinery onsite.
Set out of works
DBYD plans
Location of existing services using cable locator
Pot holing for verification
Engage site specific safety plans
Safety signage and equipment
Establish and maintain environmental protection devices for the duration of works (including environmental plan)
Allowance for bank guarantees and insurances
Prepare 15,000m2 on both fields
Next step in the process was the Surface Preparation and Cultivation:
Total kill herbicide 2 applications 7 days apart
Blecavator to 100mm depth x 3 directions
Import premium topsoil blend TS8000P.B in truck and dog loads
Laser Level to achieve 1% fall
Supply and Apply Amendmax X—Change 150-OM Soil Conditioner
Final Trim and Brush Surface for placement of turf
Turf Installation — 15,000m2 on both fields
Once the site was prepared, we would then be ready for the turf installation. The turf was purposely grown and inspected at our turf farm at Woodford. We would harvest and install the turf on the same day to allow for minimal stress on the turf.
Supply and lay Wintergreen couch Turf
Turf supplied in slabs
Turf supplied on sandy loam growing medium
Smooth Roll in 2 directions
Supply and apply Oxamax herbicide plus fertilizer 18-10-19 at 340kg/Ha
Turf treated with Accelepryn 1 week prior to harvest
Maintenance — 8 weeks
After the turfing had been done the maintenance period works would start.
Mowing during establishment and brush cut fence lines
Top Dress with TS2000 at Approximately 10mm Cover
Fertilise with Slow Release Fertiliser — Sports Turf Classic Starter 18-10-19 at 200kg/Ha
Weed and pest management applications
Prepared area ready laser graded at 1% ready for turf installationIrrigation on immediately that turf is installed in sections. Please note Irrigation was done by Project Irrigation which was part of another project all together and not under us.First batch of turf starting to be harvested for Talobilla Baseball FieldsTurf HarvestingFinal Day of Turf install on Main field